Abu Dhabi turns its attention to efficiency

As Abu Dhabi’s groundbreaking $1.6bn Strategic Tunnel Enhancement Programme (STEP) nears completion, the emirate’s wastewater company is now turning its focus to improving and rehabilitating existing infrastructure.

“We have spent the past 12 years investing in new infrastructure to reach a stage of calmness,” says Alan Thomson, managing director at Abu Dhabi Sewerage Services Company (ADSSC). “Now we are not firefighting, we are moving on to a tactical investment programme.”

Pioneer project

The complex STEP scheme is the Middle East’s first deep-tunnel sewer network, and it is set to be fully operational in 2018, 10 years after the first construction tenders were issued for the project.

“Part of the tunnel is operational, with 300,000 cubic metres a day [cm/d] already pumping through the system,” says Thomson. “Work is ongoing to [finish] the pumping station, with a view to completion in the first quarter of 2018.”

Developed to upgrade Abu Dhabi’s strained sewerage network, the majority of which was installed in the 1970s, STEP consists of a 41-kilometre tunnel, starting on Abu Dhabi island and running south to the mainland, descending from 24 metres below ground level to a depth of 80 metres in some places.

With the megaproject nearing full commissioning, ADSSC is now turning its focus to upgrading other existing infrastructure to complement the new deep-tunnel system.

“We are continuing to keep an eye on Abu Dhabi’s growth plans and once STEP is in full use, we will look at its impact on the rest of the system to see what needs to be rehabilitated to ensure more efficient operation of the network,” says Thomson.

With the emirate seeking to rationalise spending as a result of the drop in oil revenues and together with the slowdown in some areas of its development programme, the focus of ADSSC’s tactical investment programme will be increasing the efficiency of existing wastewater infrastructure. A key part of this will involve utilising innovative technology to improve the monitoring and performance of the network.

“Using technology and innovation will improve network efficiency and reduce [our] carbon footprint.”
“Supervisory control and data acquisition [Scada] systems have come a long way, and we are looking at how we can use this to catch more data and improve performance,” says Thomson. “Systems are now able to give qualitative analysis as well as quantitative analysis, and we are determining which system we will go for.”

According to Thomson, better data collection will increase knowledge of the system, and will be able to detect unwanted discharges and rogue substances entering the network.

The combination of more in-depth quantitative and qualitative analysis will also prepare the wastewater services provider for any future changes to the charging of sewerage in the emirate.

“If [Abu Dhabi] decides to go into a system with peak and off-peak tariffs, we will be able to use the system for storage so we can pump off-peak,” says Thomson.

Integrating the latest technology into the system will also help the UAE meet its ambitious environmental targets.

“Using technology and innovation will improve network efficiency and reduce [our] carbon footprint,” says Thomson.

ADSSC has enlisted international consultants to assist with the future planning and development of its sewerage network. In January, it awarded an AED25m ($6.8m) contract to the local office of Austria’s ILF Consulting Engineers to provide consultancy services on the fifth phase of the emirate’s sewerage network upgrade. ADSSC’s commitment to long-term planning has been further boosted by the completion of an update to the emirate’s wastewater masterplan, which was completed by US consultancy MWH Global earlier this year.

Dubai tunnel

Following Abu Dhabi’s lead, neighbouring emirate Dubai is also seeking to develop a deep-tunnel sewer network, which could cost up to $8.2bn.

The proposed Dubai Strategic Sewerage Tunnel Project would comprise two main tunnels with a total length of 75km. The Bur Dubai deep tunnel is planned to have a total length of 50km and the Deira tunnel will have a total length of 25km. The tunnels will be supported by about 140km of link sewers and two major pump stations. The tunnels will reach depths of up to 90 metres below ground level.

The deep-tunnel sewerage network and two major pumping stations would replace 11 major pump stations and more than 100 smaller ones currently serving the wastewater network. In May 2016, Dubai Municipality awarded US-based Parsons the consultancy services contract for the duration of the scheme, including feasibility studies, the preliminary design, tender preparation and support.

Dubai had originally planned to procure the project through conventional engineering, procurement and construction (EPC) packages. MEED revealed in June that the municipality had appointed the Netherlands’ KPMG to advise on and assist with preparations for developing the network under a public-private partnership (PPP) contract, which would be the first of its kind in the region.

Although Abu Dhabi currently has no further plans for PPPs in the wastewater sector, successful implementation in Dubai may open the way for new partnerships with the private sector in the longer term.

“[PPP] has been used for treatment plants in Abu Dhabi, but currently there are no plans for further use,” says Thomson. “However, we will keep an eye on what Dubai is doing and if it works, it could be an option in the future.” 

Related Posts
Taskforce demands post-Covid infrastructure spend
The infrastructure financing gap has grown even wider in the wake of the Covid-19 pandemic The G20/OECD Taskforce on Long-term Investment has said infrastructure investment will help alleviate the impact of ...
READ MORE
Construction faces greater challenges in 2021
Slump in contract awards points to tougher market conditions for construction companies next year While the Covid-19 pandemic has not thwarted ongoing projects in the GCC, plans for future developments are ...
READ MORE
Egypt rail projects require sustained political will
Historical indecision does not automatically inspire optimism among rail contractors The plan to build, finance and maintain two urban monorail systems and a high-speed railway network in Egypt has moved rapidly between January, when consultants ...
READ MORE
Dubai spending cuts are unsurprising amid Covid-19
Government decision to avoid cost overruns exposes contractors to project losses The Dubai government’s decision to put future projects on hold is unsurprising as Covid-19 weighs down on global economies. While the government ...
READ MORE
Dubai plans a lasting legacy for Expo 2020
When Expo 2020 Dubai closes in April 2021, the site will be converted into a test bed for global innovation Dubai plans to develop a new city on the 4.38 square-kilometre ...
READ MORE
States deliberate on stranded South Asian workers
The UAE's offer to repatriate expatriates has not been taken up by India Discussions are under way to repatriate foreign workers, including Indian and Pakistani nationals, from the UAE as the ...
READ MORE
Construction
There are more than $155bn of residential and mixed-use schemes still on hold The decision by Bahrain’s Judicial Committee for the Settlement of Stalled Real Estate Projects plans to auction the ...
READ MORE
Pandemic drives Gulf governments to debt markets
Foreign currency bonds worth about $40bn have been issued so far this year, with more to come as Gulf governments try to bridge large budget deficits This year has seen a ...
READ MORE
Dubai eyes rare bond issuance
Around $2bn could be issued in Islamic loans and bonds as government lending to Emirates tops AED7.3bn The Dubai government plans to offer bonds and Islamic securities as it contends with ...
READ MORE
Dubai’s construction market dropped sharply in second quarter
Contract awards have failed to keep pace with the large volume of projects that are now being completed Dubai’s construction market retreated sharply during the second quarter of this year, with ...
READ MORE
Taskforce demands post-Covid infrastructure spend
Construction faces greater challenges in 2021
Egypt rail projects require sustained political will
Dubai spending cuts are unsurprising amid Covid-19
Dubai plans a lasting legacy for Expo 2020
States deliberate on stranded South Asian workers
Stalled real estate projects are still an issue
Pandemic drives Gulf governments to debt markets
Dubai eyes rare bond issuance
Dubai’s construction market dropped sharply in second quarter
09 November, 2017 | .By ANDREW ROSCOE